Minerals Development Act 2017

Outcome of public participation on rehabilitation plan

138. (1) Where public participation has taken place in accordance with section 137 the rehabilitation authority shall—

(a) take due account of the outcome of the public participation in its preparation or, as the case may be, revision, of the rehabilitation plan, and

(b) make a copy of the plan or revised plan available to the public at the offices of the Department of Communications, Climate Action and Environment and on the Department’s website.

(2) The procedure for seeking judicial review of the preparation or revision of a rehabilitation plan and the costs of any such judicial review are governed by Part 2 of the Environment (Miscellaneous Provisions) Act 2011 .