Planning and Development (Amendment) Act 2010

Amendment of section 42A of Principal Act.

29.— Section 42A of the Principal Act (inserted by section 238 of the National Asset Management Agency Act 2009 ) is amended as follows:

(a) by the substitution of the following for subsection (1):

“(1) On application to it in that behalf a planning authority shall, as regards a particular permission, extend the appropriate period by such additional period not exceeding 5 years as the authority considers requisite to enable the development to which the permission relates to be completed provided that each of the following requirements is complied with:

(a) either—

(i) the authority is satisfied that—

(I) the development to which the permission relates was commenced before the expiration of the appropriate period sought to be extended,

(II) substantial works were carried out pursuant to the permission during that period, and

(III) the development will be completed within a reasonable time,

or

(ii) the authority is satisfied—

(I) that there were considerations of a commercial, economic or technical nature beyond the control of the applicant which substantially militated against either the commencement of development or the carrying out of substantial works pursuant to the planning permission,

(II) that there have been no significant changes in the development objectives in the development plan or in regional development objectives in the regional planning guidelines for the area of the planning authority since the date of the permission such that the development would no longer be consistent with the proper planning and sustainable development of the area,

(III) that the development would not be inconsistent with the proper planning and sustainable development of the area having regard to any guidelines issued by the Minister under section 28, notwithstanding that they were so issued after the date of the grant of permission in relation to which an application is made under this section, and

(IV) where the development has not commenced, that an environmental impact assessment, or an appropriate assessment, or both of those assessments, if required, was or were carried out before the permission was granted,

(b) the application is in accordance with such regulations under this Act as apply to it,

(c) any requirements of, or made under those regulations are complied with as regards the application, and

(d) the application is duly made prior to the end of the appropriate period.”,

(b) by the substitution of the following for subsection (2):

“(2) In extending the appropriate period under subsection (1) a planning authority may attach conditions requiring the giving of adequate security for the satisfactory completion of the proposed development, and/or may add to or vary any conditions to which the permission is already subject under section 34(4)(g).”,

(c) by the insertion of the following after subsection (7):

“(8) Notwithstanding subsection (1) or (4), where a decision to extend an appropriate period has been made by a planning authority prior to the coming into operation of this section, the planning authority, where an application is made to it in that behalf prior to the expiration of the period by which the appropriate period was extended, may further extend the appropriate period provided that each of the following requirements is complied with—

(i) an application is made in that behalf in accordance with regulations under section 43,

(ii) any requirements of, or made under, the regulations are complied with as regards the application, and

(iii) the authority is satisfied that the relevant development has not been completed due to circumstances beyond the control of the person carrying out the development.”.